Project Story

Waikato River

Following the worst drought on record, the treatment plant on the Waikato River could help increase Auckland’s water supply.

Aerial shot of a construction site in the woods

Fletcher Construction delivers on the mission-critical Waikato 50 Project.

The major business driver for this project was a true collaboration with multiple parties … by opening up the project, we reduced the risk of not meeting deadlines to deliver water to the residents and the economy required for post-COVID economic re-generation and stability.

Matthew Stanford

Design Interface Manager, Project Controls Manager

The Watercare authority has begun considering Auckland’s Waikato River and its associated treatment plant the water supply for the city, having suffered the worst drought on record. The plant prioritises water from the more resilient river feed, giving the water storage dams in the Hūnua and Waitakere ranges time to recharge and recover.

Currently, the treatment plant provides up to 30 percent of drinking water for the Auckland region. However, this project enables an additional 50 million litres per day through the treatment plant.

Construction crane moving pieces

The Watercare authority has begun considering Auckland’s Waikato River and its associated treatment plant the water supply for the city, having suffered the worst drought on record. The plant prioritises water from the more resilient river feed, giving the water storage dams in the Hūnua and Waitakere ranges time to recharge and recover.

Currently, the treatment plant provides up to 30 percent of drinking water for the Auckland region. However, this project enables an additional 50 million litres per day through the treatment plant.

Water tank

Blowing benchmarks out of the water

Fletcher Construction’s unique contribution to the project saw a two-year delivery timeline achieved in under nine months. Knowing non-traditional shift hours would be required to meet such an ambitious timeline, the teams have operated on double shifts. Often, they even sacrificed personal time so that the project delivery could be accelerated by 75 percent. All this was done to ensure New Zealand’s largest city has enough water to power itself through a post-pandemic recovery.

Resources for Selecting the Best Construction Software

Contractor using Procore on a tablet

Construction Project Management Software Buyer's Guide

A step-by-step guide for evaluating today’s software solutions.

When it comes to investing in software, every step in the decision making process is important, and one misstep can cost you. We've compiled expert tips from top software procurement experts to help you understand how to...

Ready to see it in action?

Stop searching across apps to understand what's really happening on your projects. Request a demo now.

(2,698)

(2,656)

(31K)

(2,810)